Exam 3: Cost Behavior
Exam 1: Introduction to Cost Management115 Questions
Exam 2: Basic Cost Management Concepts161 Questions
Exam 3: Cost Behavior132 Questions
Exam 4: Activity-Based Costing154 Questions
Exam 5: Product and Service Costing: Job-Order System102 Questions
Exam 6: Process Costing137 Questions
Exam 7: Allocating Costs of Support Departments and Joint Products143 Questions
Exam 8: Budgeting for Planning and Control167 Questions
Exam 9: Standard Costing: a Functional-Based Control Approach86 Questions
Exam 10: Decentralization: Responsibility Accounting, Performance Evaluation, and Transfer Pricing110 Questions
Exam 11: Strategic Cost Management121 Questions
Exam 12: Activity-Based Management116 Questions
Exam 13: The Balanced Scorecard: Strategic-Based Control92 Questions
Exam 14: Quality and Environmental Cost Management157 Questions
Exam 15: Lean Accounting and Productivity Measurement137 Questions
Exam 16: Cost-Volume-Profit Analysis108 Questions
Exam 17: Activity Resource Usage Model and Tactical Decision Making98 Questions
Exam 18: Pricing and Profitability Analysis102 Questions
Exam 19: Capital Investment97 Questions
Exam 20: Inventory Management: Economic Order Quantity, Jit, and the Theory of Constraints98 Questions
Select questions type
The cost function derived by the least-squares cost estimation method
(Multiple Choice)
4.8/5
(37)
In a traditional cost management system, cost behavior is assumed to be driven only by
(Multiple Choice)
4.9/5
(45)
Figure 3-3 Mork Company has four process engineers that are each able to process 1,500 design changes.Last year 5,250 design changes were produced by the four engineers.Each engineer is paid $60,000 per year.
-
Refer to Figure 3-3.What is the unused capacity in dollars?
(Multiple Choice)
4.8/5
(33)
Which of the following statements is TRUE about fixed and variable costs?
(Multiple Choice)
4.9/5
(35)
The following information was taken from a computer printout generated with the least-squares method for use in estimating overhead costs:
The cost formula is

(Multiple Choice)
4.8/5
(27)
Assuming costs are represented on the vertical axis and volume of activity on the horizontal axis, which of the following costs would be represented by a line that is parallel to the horizontal axis?
(Multiple Choice)
4.7/5
(41)
Figure 3-4 The following information is available for electricity costs for the last six months of the year:
- Refer to Figure 3-4.Using the high-low method, estimated variable cost per unit of production is

(Multiple Choice)
4.9/5
(32)
Figure 3-7 The following computer printout estimated overhead costs using regression:
Please find the following statistical table
During the last accounting period 10,000 DLH were worked.
-
Refer to Figure 3-7.Find the t-value for a 90 percent confidence level.


(Multiple Choice)
4.7/5
(36)
What is the difference between a correlation equal to -1 and a correlation equal to +1?
(Multiple Choice)
4.8/5
(44)
Figure 3-6 The following information is available for maintenance costs:
-Refer to Figure 3-6.Using a computer or calculator, compute the estimate of maintenance costs at 100 units of production using the method of least squares.This value would be

(Multiple Choice)
4.9/5
(38)
Figure 3-7 The following computer printout estimated overhead costs using regression:
Please find the following statistical table
During the last accounting period 10,000 DLH were worked.
-
Refer to Figure 3-7.What is the confidence interval for the predicted overhead cost rounded to the nearest whole number for a 90 percent confidence level?


(Multiple Choice)
4.8/5
(48)
The learning curve that decreases by a constant percentage each time the cumulative quantity doubles is known as the
(Multiple Choice)
4.7/5
(35)
The cost behavior method that may use time and motion studies to determine the activities and amounts for cost behavior analysis is
(Multiple Choice)
4.9/5
(45)
Figure 3-2 A company usually processes 20,000 orders at a total cost of $300,000.During the year, only 16,000 orders were processed.
-
Refer to Figure 3-2.What is the cost of resource usage?
(Multiple Choice)
4.8/5
(28)
Figure 3-3 Mork Company has four process engineers that are each able to process 1,500 design changes.Last year 5,250 design changes were produced by the four engineers.Each engineer is paid $60,000 per year.
-
Refer to Figure 3-3.Calculate the activity rate per change order.
(Multiple Choice)
4.9/5
(34)
__________ explain changes in costs as units produced change.
(Multiple Choice)
4.8/5
(33)
Figure 3-8 The following computer printout estimated overhead costs using multiple regression:
During the year the company used 1,000 setup hours and 500 parts.
-
Refer to Figure 3-8.The degrees of freedom for the model is

(Multiple Choice)
4.9/5
(42)
Showing 61 - 80 of 132
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)