    Schedule Variance (SV) Equals Earned Value (EV) Minus Planned Value
Solved

Schedule Variance (SV) Equals Earned Value (EV) Minus Planned Value

Question 69

Question 69

True/False

Schedule variance (SV) equals earned value (EV) minus planned value (PV), or SV = EV - PV.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q64: The monitoring and control process begins very

Q65: In the _ management knowledge area, the

Q66: In configuration management process, this is identifying

Q67: Estimate to complete (ETC) is the revised

Q68: Quantitative assessments are assessments such as user-reported

Q70: _ (which happens during IT projects when

Q71: _ and control involves a set of

Q72: In the time management knowledge area, the

Q73: In configuration management, this is the release

Q74: The _ Management knowledge area consists of

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines