Question 61
Multiple Choice
With respect to monitoring and control, which of the following elements should NOT have been defined during the planning phase of the project?
Question 62
True/False
To increase the chances for biased reporting, the process should be as automated as possible, and there needs to be a separation of responsibilities.
Question 63
Essay
Name and describe the four elements in the configuration management process.
Question 64
True/False
The monitoring and control process begins very early in the life of a project and overlaps all other processes.
Question 65
Multiple Choice
In the ________ management knowledge area, the processes concerned with monitoring and control are verifying scope and controlling scope.
Question 66
Multiple Choice
In configuration management process, this is identifying the structure of the product, its components, and their type and making them unique and accessible in some form to the team.
Question 67
True/False
Estimate to complete (ETC) is the revised estimate for the work remaining, as determined by the project team.
Question 68
True/False
Quantitative assessments are assessments such as user-reported likes / dislikes about the product and team member-reported task completion percentage estimates.
Question 69
True/False
Schedule variance (SV) equals earned value (EV) minus planned value (PV), or SV = EV - PV.
Question 70
Multiple Choice
________ (which happens during IT projects when the scope of the system is allowed to continually grow) is one of the key contributors to projects costing more than originally budgeted and lasting longer than originally scheduled.
Question 71
Multiple Choice
________ and control involves a set of processes from eight of the nine knowledge areas.
Question 72
True/False
In the time management knowledge area, the process concerned with monitoring and control is controlling the schedule.
Question 73
Multiple Choice
In configuration management, this is the release of a product and changes to it throughout the product life cycle by having in place controls that ensure consistent releases via the creation of a baseline product.