Multiple Choice
In this tool for estimating percentage complete, when a task or work package is started, it is immediately assigned a 50 percent complete status until it is completed and then is set to 100 percent complete.
A) 0-100 percent rule
B) 50-50 percent rule
C) Interval percent rule
D) EVM
Correct Answer:

Verified
Correct Answer:
Verified