Multiple Choice
With this method of percentage complete estimation, a team agrees to use a set of completion milestones such as thirds (33 percent, 67 percent, 100 percent) or fourths (25 percent, 50 percent, 75 percent, 100 percent) .
A) 0-100 percent rule
B) 50-50 percent rule
C) Interval percent rule
D) EVM
Correct Answer:

Verified
Correct Answer:
Verified