The Goal of the Execution Phase Is to Work on Each

Question 24

Multiple Choice

The goal of the execution phase is to work on each task defined in the ________ to produce the identified outcomes and to follow the defined or as-changed project schedule.


A) scope statement
B) project schedule
C) WBS
D) risk management plan

Correct Answer: