Multiple Choice
On most, if not all, medium to large IT projects, a project manager will never see any of the application code generated by the software developers and must spend time influencing the ________ that will lead to better-written software.
A) processes
B) human resources
C) technical resources
D) vendors
Correct Answer:

Verified
Correct Answer: