Multiple Choice
________ task dependencies are based on work performed by an entity outside the organization or business unit.
A) Mandatory
B) Discretionary
C) External
D) Project
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q59: List the processes of the Time Management
Q60: The acronym PERT stand for:<br>A) Program Estimation
Q61: Project schedule development determines the planned start
Q62: Resource loading is the process of rescheduling
Q63: The precedence diagram method (PDM) of constructing
Q65: The activity resource estimating process consists of
Q66: The _ process is concerned with determining
Q67: _ task dependencies are defined based on
Q68: CPM produces what key piece of information?<br>A)
Q69: The critical path method, unlike the critical