CPM Produces What Key Piece of Information

Question 68

Multiple Choice

CPM produces what key piece of information?


A) The amount of slack, or float, for each activity in the schedule.
B) The critical path, which is the longest path through the schedule or the shortest time in which the project can be completed.
C) Neither A nor B
D) Both A and B