Multiple Choice
Which formula is used to calculate the PERT weighted average?
A) Optimistic estimate + 6 (Most likely estimate) + Pessimistic 4
B) Optimistic estimate + 4 (Most likely estimate) + Pessimistic 6
C) Most likely estimate + 4 (Optimistic estimate) + Pessimistic 6
D) Pessimistic estimate + 4 (Most likely estimate) + Optimistic 6
Correct Answer:

Verified
Correct Answer:
Verified