Multiple Choice
What is the critical path of a project?
A) The path through the schedule with the highest priority tasks.
B) The path through the schedule with the highest cost resources.
C) The longest path through the schedule or the shortest time in which the project can be completed.
D) The shortest path through the schedule.
Correct Answer:

Verified
Correct Answer:
Verified