Multiple Choice
Resource ________ is the process of rescheduling on the project schedule activities that have available slack to achieve a more balanced distribution of resource usage.
A) loading
B) leveling
C) assignment
D) estimation
Correct Answer:

Verified
Correct Answer:
Verified