Multiple Choice
The critical ________ method, unlike the critical path method, looks at more than just time and does not assume that you have unlimited resources to accomplish the activities on your project.
A) chain
B) roadmap
C) sequence
D) resource
Correct Answer:

Verified
Correct Answer:
Verified