Multiple Choice
The output from ________ planning is used as part of the overall project plan and can consist of one or all of these elements: budget estimates, units of measure, links to accounting control accounts, allowable variances, methods used to track progress such as earned value, and stakeholder reporting formats.
A) resource
B) project
C) schedule
D) cost