Multiple Choice
A ________,which is conducted by the project manager,involves determining if the information system makes sense for the organization from an economic and operational standpoint.
A) Tool
B) Feasibility study
C) Data flow
D) Methodology
Correct Answer:

Verified
Correct Answer:
Verified