Multiple Choice
Which of the following is FALSE with respect to a task in a project plan?
A) It can be done by one person only.
B) It has a single and identifiable deliverable.
C) It has a known method or technique.
D) It has well-accepted predecessor and successor steps.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q63: A _,which is conducted by the project
Q64: _ is the third phase of the
Q65: Which of the following is the first
Q66: Which of the following is FALSE in
Q67: A network diagram depicts a Gantt chart.
Q69: Which of the following is FALSE in
Q70: Interpreting system requests and specifications is not
Q71: Why are systems development projects initiated? Provide
Q72: List at least 3 activities of a
Q73: Which of the following is NOT an