Multiple Choice
The distinguishing feature of a network diagram is that the ordering of tasks is shown by connecting tasks-depicted as ________ or ovals-with their predecessor and successor tasks.
A) Circles
B) Diamonds
C) Ellipticals
D) Rectangles
Correct Answer:

Verified
Correct Answer:
Verified