Multiple Choice
Which of the following is NOT true of a project communication plan?
A) It outlines the communication procedures among management,project team members,and the customer.
B) It includes when and how written and oral reports will be provided by the team.
C) It does not define communication with vendors and external contractors.
D) It includes how team members will coordinate work.
Correct Answer:

Verified