Which of the following is FALSE with respect to the Gantt chart and network diagram?


A) Gantt charts visually show the duration of tasks,whereas a network diagram visually shows the sequence dependencies between tasks.
B) Gantt charts visually show the time overlap of tasks,whereas a network diagram does not show time overlap but does show which tasks could be done in parallel.
C) Gantt charts visually show the time overlap of tasks,whereas a network diagram shows time overlap but does show which tasks could be done in parallel.
D) Some forms of Gantt charts can visually show slack time available within an earliest start and latest finish duration.