menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Computing
  3. Study Set
    Modern Systems Analysis and Design Study Set 2
  4. Exam
    Exam 3: Managing the Information Systems Project
  5. Question
    The Critical Path Represents the ________ Time in Which a Project
Solved

The Critical Path Represents the ________ Time in Which a Project

Question 86

Question 86

Multiple Choice

The critical path represents the ________ time in which a project can be completed.


A) Shortest
B) Longest
C) Farthest
D) Tallest

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q81: _ is a critical path scheduling technique

Q82: Tasks that are _ in scope will

Q83: Define and describe the PERT technique.

Q84: A critical path refers to a sequence

Q85: Identifying,assessing,and managing the risks and day-to-day changes

Q87: Defining tasks in too much detail will

Q88: What is the next step taken after

Q89: Which of the following is NOT true

Q90: Which of the following is FALSE with

Q91: Executing the project is the third phase

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines