A Critical Path Refers to a Sequence of Task Activities

Question 84

Multiple Choice

A critical path refers to a sequence of task activities whose ________ and ________ directly affect the completion date of a project.


A) Duration; network
B) Order; network
C) Task; sequence
D) Order; duration