The path in a precedence network with the longest duration is the critical path.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q5: What is the estimated expected (mean)duration (in

Q6: The manager of a National Forest is

Q7: The Project Manager is about to begin

Q10: Project planning determines how the project is

Q11: Indirect cost for a project is $2500

Q12: A project manager should not be concerned

Q13: A hierarchical listing of what must be

Q14: Using the information given,do the following:<br>(i)Identify the

Q20: Although PERT and CPM were originally developed

Q59: Project managers are sometimes able to reduce

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines