Solved

The Project Manager Is About to Begin a Project Comprised

Question 7

Multiple Choice

The Project Manager is about to begin a project comprised of the following six activities: The Project Manager is about to begin a project comprised of the following six activities:   What is the estimated expected (mean) duration for activity E? A) 91 days B) 99 days C) 100 days D) 101 days E) 115 days What is the estimated expected (mean) duration for activity E?


A) 91 days
B) 99 days
C) 100 days
D) 101 days
E) 115 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions