Which of the following is not an advantage(s) the PERT/CPM technique has over a Gantt chart?
A) its ability to reveal relationships among activities.
B) it illustrates multiple paths as a project network.
C) it indicates which activities are most critical.
D) it indicates the implications of delays in activities.
E) it is a more complex scheduling system.
Correct Answer: