Multiple Choice
A project superintendent is about to begin work on a freeway resurfacing project,which is comprised of the following five activities: What is the estimated standard deviation of the duration for activity E?
A) 0 weeks
B) 1 week
C) 2 weeks
D) 3 weeks
E) 4 weeks
Correct Answer:

Verified
Correct Answer:
Verified