Multiple Choice
In precedence network analysis,knowing the slack time allows managers to:
A) delay critical activities.
B) extent the project if necessary.
C) increase the critical path.
D) pay attention to activities that could delay the project.
E) decrease the project duration.
Correct Answer:

Verified
Correct Answer:
Verified