Multiple Choice
When developing probabilistic estimates of project duration,it is necessary to know which of the following?
A) The mean and variance of every activity
B) The mean and variance of activities on the critical path
C) The standard deviation of activities on the critical path
D) Each activity's probability of completion
E) The distribution of activity durations
Correct Answer:

Verified
Correct Answer:
Verified
Q10: Project planning determines how the project is
Q11: Indirect cost for a project is $2500
Q12: A project manager should not be concerned
Q13: A hierarchical listing of what must be
Q14: Using the information given,do the following:<br>(i)Identify the
Q16: What are the estimated slack times (in
Q17: The Project Manager is about to begin
Q18: A Gantt chart provides a visual representation
Q19: A project has the activities and activity
Q20: In precedence network analysis,knowing the slack time