Multiple Choice
A project manager for Durable Construction Co.is about to build a house involving the following six activities: What is the estimated expected (mean) duration for activity E?
A) 35 days
B) 36 days
C) 39 days
D) 40 days
E) 45 days
Correct Answer:

Verified
Correct Answer:
Verified