Solved

In the Probabilistic Approach to Precedence Network Analysis,the Duration Estimate

Question 62

Multiple Choice

In the probabilistic approach to precedence network analysis,the duration estimate that is given the highest weighting in calculating the expected duration for an activity is:


A) duration of the immediately prior activity.
B) duration of the immediately following activity.
C) most likely duration.
D) optimistic duration.
E) pessimistic duration.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions