Multiple Choice
Which of the following is not a "tool" (technique) for shop-floor control?
A) Anticipated delay report
B) Input/output (I/O) control
C) Daily dispatch lists
D) Product structure tree
E) Schedule/control Gantt chart
Correct Answer:

Verified
Correct Answer:
Verified