The table below contains information about five jobs waiting to be processed at work station number three. Using the CR rule,the sequence of jobs would be:
A) c-a-b-d-e.
B) a-b-d-e-c.
C) d-e-b-a-c.
D) c-a-b-e-d.
E) e-d-b-a-c.