Short Answer
Given the following data for jobs awaiting processing at a manufacturing cell in which jobs are first processed by machine A,then by Machine B:
In developing the sequence which will minimize make-span,what is the initial job to be placed in the schedule sequence?
Correct Answer:

Verified
Correct Answer:
Verified