Multiple Choice
A process designed to handle purchasing and scheduling the production of dependent-demand components is:
A) economic part-period (EPP) .
B) lot-for-lot (LFL) .
C) economic order quantity (EOQ) .
D) material requirements planning (MRP) .
E) economic run size (ERS) .
Correct Answer:

Verified
Correct Answer:
Verified
Q37: The following is a list of components
Q38: The input used in MRP that lists
Q39: The MRP approach that immediately updates only
Q40: MRP usually involves inventory items that have
Q41: The term pegging refers to identifying the
Q43: A master production schedule (MPS)is the principal
Q44: The planned-order releases at one level of
Q45: Load reports of capacity may be misleading
Q46: ERP systems are based on software modules
Q47: Given an order cost of $100,a,per period