The Input Used in MRP That Lists the Assemblies,subassemblies,parts,and Raw

Question 38

Multiple Choice

The input used in MRP that lists the assemblies,subassemblies,parts,and raw materials needed to produce one unit of finished product is the:


A) master production schedule.
B) bill of material.
C) inventory-records.
D) assembly-time chart.
E) net-requirements chart.

Correct Answer: