Multiple Choice
Which is true of a net-change MRP?
A) It is a batch-type system which is updated periodically.
B) It generates exception reports.
C) The basic production plan is modified to reflect changes as they occur.
D) It is used to authorize the execution of planned orders.
E) It indicates the amount and timing of future changes.
Correct Answer:

Verified
Correct Answer:
Verified