Question 60

Multiple Choice

Great Product,Ltd.has just received an order for 100 Whozats,which must be ready for delivery at the start of week six.An MRP planner has prepared the following table showing product structure,lead times (orders are lot-for-lot) ,and quantities on hand: Great Product,Ltd.has just received an order for 100 Whozats,which must be ready for delivery at the start of week six.An MRP planner has prepared the following table showing product structure,lead times (orders are lot-for-lot) ,and quantities on hand:   When should an order for Wherezats be released? A) At the start of week 2. B) At the start of week 3. C) At the start of week 4. D) At the start of week 5. E) At the start of week 6. When should an order for Wherezats be released?


A) At the start of week 2.
B) At the start of week 3.
C) At the start of week 4.
D) At the start of week 5.
E) At the start of week 6.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions