Multiple Choice
QRS Corp.is designing a product layout for a new product.They plan to use this production line ten hours a day in order to meet forecasted demand of 900 units per day.The following table describes the tasks necessary to produce this product: For output to equal forecasted demand,what should be the actual cycle time for this production?
A) 32 seconds
B) 38 seconds
C) 40 seconds
D) 76 seconds
E) 152 seconds
Correct Answer: