The Maker of the World-Famous Widget Needs to Design a Product

Question 20

Multiple Choice

The maker of the world-famous Widget needs to design a product layout for a new product,the amazing "Thatsit".The company plans to use this new production line eight hours a day in order to meet projected demand of 1,440 units per day.The following table describes the tasks involved in the production of a "Thatsit". The maker of the world-famous Widget needs to design a product layout for a new product,the amazing  Thatsit .The company plans to use this new production line eight hours a day in order to meet projected demand of 1,440 units per day.The following table describes the tasks involved in the production of a  Thatsit .   Without considering projected demands,what is the minimum possible cycle time for this production line? A) 54 seconds B) 14 seconds C) 12 seconds D) 10 seconds E) 4 seconds Without considering projected demands,what is the minimum possible cycle time for this production line?


A) 54 seconds
B) 14 seconds
C) 12 seconds
D) 10 seconds
E) 4 seconds

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions