Multiple Choice
A company needs to rebalance a product layout for producing a redesigned product.They plan to use the assembly line 6 hours in order to meet projected demand of 2,160 license plates each day.The following table describes the tasks involved in the production of this product: For output to equal projected demand,what is the minimum number of workstations needed?
A) 2
B) 2.8
C) 3
D) 4
E) 5
Correct Answer:

Verified
Correct Answer:
Verified
Q71: If a line is balanced with 90
Q72: A company needs to rebalance a product
Q73: Given the following line balance data:<br> <img
Q74: Which of the following is not used
Q75: Which of the following most closely describes
Q77: Which of the following is not a
Q78: The first step in process design is
Q79: The process flow diagram for services is
Q80: The theoretical minimum number of workstations for
Q81: In which type of operations process are