Question 76

Multiple Choice

A company needs to rebalance a product layout for producing a redesigned product.They plan to use the assembly line 6 hours in order to meet projected demand of 2,160 license plates each day.The following table describes the tasks involved in the production of this product: A company needs to rebalance a product layout for producing a redesigned product.They plan to use the assembly line 6 hours in order to meet projected demand of 2,160 license plates each day.The following table describes the tasks involved in the production of this product:   For output to equal projected demand,what is the minimum number of workstations needed? A) 2 B) 2.8 C) 3 D) 4 E) 5 For output to equal projected demand,what is the minimum number of workstations needed?


A) 2
B) 2.8
C) 3
D) 4
E) 5