A Company Needs to Rebalance a Product Layout for Producing

Question 72

Multiple Choice

A company needs to rebalance a product layout for producing a redesigned product.They plan to use the assembly line 6 hours in order to meet projected demand of 2,160 license plates each day.The following table describes the tasks involved in the production of this product: A company needs to rebalance a product layout for producing a redesigned product.They plan to use the assembly line 6 hours in order to meet projected demand of 2,160 license plates each day.The following table describes the tasks involved in the production of this product:   For output to equal projected demand,what will be the efficiency of the assembly line that uses the minimum number of workstations? A) 0.0% B) 6.7% C) 70.0% D) 93.3% E) 100% For output to equal projected demand,what will be the efficiency of the assembly line that uses the minimum number of workstations?


A) 0.0%
B) 6.7%
C) 70.0%
D) 93.3%
E) 100%

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions