Multiple Choice
Which of the following is not one of the four principles of bottleneck management?
A) Release work orders to the system at the bottleneck's capacity pace.
B) Lost time at the bottleneck is lost system capacity.
C) Increasing capacity at non-bottleneck stations is a mirage.
D) Increased bottleneck capacity is increased system capacity.
E) Bottlenecks should be moved to the end of the system process.
Correct Answer:

Verified
Correct Answer:
Verified