Multiple Choice
Which of the following statements regarding PERT times is true?
A) The optimistic time estimate is an estimate of the minimum time an activity will require.
B) The optimistic time estimate is an estimate of the maximum time an activity will require.
C) The probable time estimate is calculated as t = (a + 4m + b) .
D) Pessimistic time estimate is an estimate of the minimum time an activity will require.
E) Most likely time estimate is an estimate of the maximum time an activity will require.
Correct Answer:

Verified
Correct Answer:
Verified
Q3: What was the name of the construction
Q16: The network analysis method that allows activity
Q39: In PERT analysis, the identification of the
Q79: Activity D on a CPM network has
Q82: The main difference between PERT and CPM
Q85: Which of the following statements regarding CPM
Q88: Which of the following statements concerning CPM
Q89: A project organization that becomes permanent is
Q91: An activity on a PERT network has
Q104: The _ has established a code of