Multiple Choice
Which of the following statements concerning CPM activities is False?
A) The early finish of an activity is the early start of that activity plus its duration.
B) The late finish is the earliest of the late start times of all successor activities.
C) The late start of an activity is its late finish less its duration.
D) The late finish of an activity is the earliest late start of all preceding activities.
E) The early start of an activity is the latest early finish of all preceding activities.
Correct Answer:

Verified
Correct Answer:
Verified
Q3: What was the name of the construction
Q39: In PERT analysis, the identification of the
Q79: Activity D on a CPM network has
Q85: Which of the following statements regarding CPM
Q86: Which of the following statements regarding PERT
Q89: A project organization that becomes permanent is
Q91: An activity on a PERT network has
Q92: A contractor's project being analyzed by PERT
Q93: Consider the network pictured below.<br>a. Enumerate all
Q104: The _ has established a code of