Multiple Choice
Five welding jobs are waiting to be processed. Their processing times and due dates are given below. Using the critical ratio dispatching rule, in which order should the jobs be processed? All dates are specified as days from Today.
A) B, D, A, E, C
B) C, D, A, B, E
C) C, E, A, D, B
D) E, B, A, D, C
E) none of the above
Correct Answer:

Verified
Correct Answer:
Verified