Multiple Choice
Which of the following statements regarding finite capacity scheduling (FCS) is false?
A) Finite capacity scheduling is well suited for dynamic scheduling environments.
B) Finite capacity scheduling overcomes the disadvantages of systems based exclusively on rules.
C) Finite capacity scheduling is very powerful, but does not allow for rapid changes.
D) Finite capacity scheduling often gets its data from the output of an MRP system.
E) None; all of the above are true.
Correct Answer:

Verified
Correct Answer:
Verified
Q26: Which of the following is an aid
Q43: In retail outlets, customers are usually processed
Q55: Machines A, B, C, and D have
Q56: A manufacturer has the following jobs waiting
Q62: Five welding jobs are waiting to be
Q64: Which of the following statements regarding scheduling
Q75: The constant work-in-process (ConWIP) card aids input-output
Q81: The three components that can lead to
Q109: The work-center master file contains data such
Q120: Explain, in your own words, how backward