Solved

Conventional MRP Uses Time Buckets That Do Not Recognize Capacity

Question 70

Multiple Choice

Conventional MRP uses time buckets that do not recognize capacity limits, and in fact ignores capacity issues. A more realistic scheduling system that includes work center capacities and other resource availabilities is


A) aggregate planning
B) the master production schedule
C) finite capacity scheduling
D) the assignment method
E) level material use

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions