Complete the table, find average lateness, find average completion time, and average number of jobs in the system. Assume all durations are in days and that the jobs are processed at the shop in the order that they arrive (A then B then C then D).
 Tob  Process Time  Flow Time  Due Date  Lateness  A 5B39C212D54 Sum 15(3.75) Average) 15(3.75)XXXX\begin{array}{|l|l|l|l|l|}\hline \text { Tob } & \text { Process Time } & \text { Flow Time } & \text { Due Date } & \text { Lateness } \\\hline \text { A } & 5 & & & \\\hline \mathrm{B} & 3 && 9 \\\hline \mathrm{C} & 2 && 12 \\\hline \mathrm{D} & 5 && 4 \\\hline \text { Sum } & 15(3.75) & \\\hline \text { Average) } & 15(3.75)&& \mathrm{XXXX} \\\hline\end{array}

Correct Answer:

verifed

Verified

blured image
Avg lateness = 11/4 = 2.75 d...