Multiple Choice
Which of the following statements regarding finite capacity scheduling (FCS) is false?
A) Finite capacity scheduling allows delivery needs to be balanced against efficiency.
B) Finite capacity scheduling overcomes the disadvantages of systems based exclusively on rules.
C) Finite capacity scheduling allows virtually instantaneous change by operators.
D) Finite capacity scheduling software formalizes the same data needed in any manual system.
E) None; all of the above are true.
Correct Answer:

Verified
Correct Answer:
Verified
Q5: Which critical ratio value implies that a
Q37: Three jobs are to be assigned to
Q38: Five jobs are waiting for processing through
Q41: Johnson's rule sequences a set of jobs
Q45: Use Johnson's rule to determine the optimal
Q56: Which of the following best describes the
Q71: Orders are processed in the sequence in
Q75: Because facility capacity, set-up time, and run
Q92: Process-focused facilities and repetitive facilities generate forward-looking
Q102: The most appropriate sequencing rule to use