Which of the following best describes a gross material requirements plan?
A) a schedule that shows total demand for an item, and when it must be ordered from a supplier or when production must be started
B) an intermediate range plan for the scheduling of families of products
C) a chart illustrating whether capacity has been exceeded
D) a table that corrects scheduled quantities for inventory on hand
E) a schedule showing which products are to be manufactured and in what quantities
Correct Answer:

Verified
Correct Answer:
Verified
Q100: Distortion in MRP systems can be minimized
Q101: Each X requires 2 of component Y
Q102: "Phantom bills" are bills of material for
Q103: Which of the following lot-sizing techniques results
Q104: Effective use of MRP and other dependent
Q106: The minimum record accuracy required for successful
Q107: Product A is made from 2 Bs
Q108: An order for 150 units of Product
Q109: What do we mean by closed-loop MRP?
Q110: Gross material requirements do not take into