Multiple Choice
The MPS calls for 110 units of Product A. There are currently 60 of Product A on hand. Each A requires 4 of Part B. There are 20 units of B available. The net requirements for B are
A) 20
B) 120
C) 180
D) 240
E) 440
Correct Answer:

Verified
Correct Answer:
Verified